America’s Energy Infrastructure: Authorizing Pipeline Safety

Environmental Permitting and Water InfrastructureHouse Energy and Commerce Subcommittee on Energy · 2026-03-04 · 119th Congress
The House Energy and Commerce Subcommittee on Energy met to examine a discussion draft reauthorizing the Pipeline and Hazardous Materials Safety Administration's (PHMSA) pipeline safety program, which oversees 3.3 million miles of gas and liquid pipelines and whose last authorization expired in 2023 [0:35:44]. Begins at 0:13:53
Transcript
Highlights

Title

House Energy and Commerce reviews PHMSA pipeline safety reauthorization draft

Purpose

The House Energy and Commerce Subcommittee on Energy met to examine a discussion draft reauthorizing the Pipeline and Hazardous Materials Safety Administration's (PHMSA) pipeline safety program, which oversees 3.3 million miles of gas and liquid pipelines and whose last authorization expired in 20230:35:44. Administrator Paul Roberti testified on the agency's enforcement priorities, staffing, and rulemaking backlog, while Democrats criticized the Republican-drafted bill as partisan and underfunded compared to bipartisan bills passed by the House Transportation and Infrastructure Committee and Senate Commerce Committee. Begins at0:13:53

Who spoke

Chairman Bill Johnson (R-OH)0:13:53: Opened the hearing on the discussion draft reauthorizing PHMSA's pipeline safety program for five years0:16:26, later questioning Roberti on how infrastructure expansion could lower energy prices0:38:00 and on enforcement prioritization0:41:20.

Ranking Member Kathy Castor (D-FL)0:18:47: Said Republicans wrote the bill without Democratic input, let the office's authorization lapse for over two and a half years0:19:59, and noted the bill authorizes nearly $200 million per year, less than the House T&I bill0:20:57; later pressed Roberti on the 14% staffing cut0:44:23 and on reauthorizing the $1 billion pipeline replacement grant program0:45:40.

Chairman Brett Guthrie (R-KY), Full Committee Chair0:23:53: Called it a discussion draft with room for bipartisan work0:24:16, and later asked Roberti about balancing safe expansion with not limiting pipeline benefits0:48:50 and state damage prevention programs0:52:53.

Ranking Member Frank Pallone (D-NJ), Full Committee0:26:52: Said enforcement cases fell to roughly half the prior four-year average and PHMSA withdrew two ready-to-finalize safety rules0:27:34; raised the suspended reimbursements to the Pipeline Safety Trust as apparent retaliation0:28:44 and questioned a PHMSA memo waiving enforcement for pipelines tied to the administration's "energy dominance" agenda0:29:11; later pressed Roberti on the enforcement decline and the limited-enforcement-discretion notice0:54:17.

Paul Roberti, PHMSA Administrator0:32:50: Testified that safety "drives everything" the agency does, citing a $9 million penalty for a Gulf of Mexico oil spill as the highest in agency history0:55:31, and that 2025 penalty totals were the highest in agency history0:56:17; said 80% of 2025 pipeline fatalities were within state jurisdiction, with 30-40% tied to excavation damage0:53:17; discussed the Satartia, Mississippi CO2 incident and a resulting $2.8 million fine1:20:36; addressed the Sable Offshore pipeline restart following the 2015 Refugio oil spill1:48:24; and said PHMSA hopes to advance a leak detection/repair NPRM but not this year1:07:25, and an idle pipeline NPRM by fall1:03:50.

Rep. Robert Aderholt (R-AL)0:59:28: Asked whether withdrawing from the UN climate framework frees enforcement resources0:59:57 and about Keystone XL's cancellation chilling private pipeline investment1:01:14.

Rep. Scott Peters (D-CA)1:04:16: Discussed his bill with Rep. Carter and Sen. Luján to codify a methane leak detection and repair rule, citing an estimated $1.5 billion in net benefits and elimination of up to half a million metric tons of methane emissions1:05:39; asked whether PHMSA will finalize an updated leak detection rule1:06:59.

Rep. Rick Allen (R-GA)1:09:49: Discussed energy affordability and asked Roberti to describe the role of cost-benefit analysis in pipeline regulations1:11:31.

Rep. Herb Conaway (D-NJ)1:15:01: Cited the 2020 Satartia, Mississippi CO2 pipeline rupture that hospitalized at least 45 people1:15:28, and pressed Roberti on why PHMSA withdrew the CO2 pipeline safety rulemaking1:16:21, calling the current bill an even deeper funding cut1:20:06.

Rep. Troy Balderson (R-OH)1:20:36: Asked Roberti to finish explaining the Satartia CO2 response1:20:36 and about clarifying in-plant piping jurisdiction between OSHA and PHMSA1:21:58, and LNG facility rulemaking coordination with FERC1:24:27.

Rep. Jennifer McClellan (D-VA)1:25:52: Argued the bill strips requirements to consider environmental impacts amid falling enforcement1:26:34, and asked whether PHMSA can demonstrate consistent safety oversight across historically overburdened communities, noting the agency's website "looks like a black hole" per Roberti's own admission1:30:13.

Rep. Diana Harshbarger (R-TN)1:31:19: Cited over 170,000 reported damages to underground infrastructure in 2024 and nearly 9,000 incidents in Tennessee1:31:19; questioned PHMSA's technical assistance grants going to an organization with a flawed financial audit1:33:30.

Rep. Jeff Crank (D-CO)1:36:31: Pressed Roberti on whether PHMSA published a rule limiting conditions in special permits1:36:31 and on Deputy Administrator Ben Coachman's prior INGA employment as a potential conflict of interest1:38:30.

Rep. Mariannette Miller-Meeks (R-IA)1:42:09: Cited a pipeline explosion in Washington County, Iowa1:42:30; asked about public communication after incidents1:43:49 and coordination on electric transmission notification near shared pipeline rights-of-way1:46:28.

Rep. Doris Matsui (D-CA)1:47:26: Raised PHMSA's move to overrule California and authorize restart of the Sable pipeline, tied to the 2015 Refugio spill of over 120,000 gallons1:48:05, and questioned the lack of environmental review or public comment1:49:41.

Rep. William Timmons (R-SC)1:52:46: Discussed backlog rulemaking priorities1:54:07 and a discussion-draft provision expanding criminal penalties to acts that impair (not just damage) pipeline operations, such as valve tampering during protests1:56:03.

Rep. Grace Meng (D-NY)1:58:15: Questioned PHMSA's termination of nine R&D grants worth $7 million on CO2 and hydrogen pipeline safety, citing a spokesperson's "Green New Scam" comment and noting the affected institutions included Texas A&M and North Dakota universities2:02:18.

Rep. Jeff Hurd (R-CO)2:03:41: Argued state decarbonization mandates in Colorado discourage pipeline safety investment2:05:03; asked about the information-sharing program modeled on FAA practices2:08:15.

Rep. Kim Schrier (D-WA)2:09:07: Detailed a BP Olympic Pipeline oil spill discovered by a blueberry farmer that caused a state emergency and fuel shortages at SeaTac and Portland airports, the 26th reportable incident in 13 years2:09:38; pressed for quantitative leak-detection performance standards rather than qualitative ones2:12:30.

Rep. Troy Nehls (R-TX)2:14:52: Discussed Texas's nearly half-million miles of pipeline and asked how reauthorization supports ERCOT grid reliability and CO2 enhanced oil recovery pipeline safety2:16:39.

Rep. Lizzie Fletcher (D-TX)2:20:24: Noted Houston-area companies control 58% of U.S. natural gas pipeline capacity and criticized the bill's failure to reauthorize the bipartisan technology pilot program from the 2020 PIPES Act2:23:22.

Rep. Julie Fedorchak (R-ND)2:25:45: Praised state-federal partnership programs, noting states cover 80% of natural gas distribution pipelines but PHMSA funding is tracking below 60% of the authorized 80%2:28:50.

Rep. Jake Auchincloss (D-MA)2:31:20: Asked about the $12 million R&D budget and methane leak detection technology, urging tech-agnostic performance criteria2:32:39.

Rep. Kevin Mullin (D-CA)2:34:27: Cited the 2010 San Bruno pipeline explosion that killed eight people in his district, and said the bill provides at least $150 million less than the T&I bill for replacing dangerous gas distribution pipelines2:34:51.

Rep. Craig Goldman (R-TX)2:38:15: Referenced the Sandman Hotel gas explosion in downtown Fort Worth and asked what happens operationally if funding fails to keep pace with new pipeline deployment2:40:33.

Rep. Dan Meuser (R-PA)2:43:56: Discussed Pennsylvania's natural gas industry and asked how PHMSA can "future-proof" regulations to allow adoption of new technologies2:45:38.

Key moments

Castor said PHMSA's staffing has decreased more than 14% since 2024 and pipeline safety enforcement was cut in half in 20250:20:570:44:23; Roberti responded that critical inspection and enforcement divisions saw no big reductions and the agency is hiring0:44:53.

Pallone stated PHMSA opened roughly half as many enforcement cases in 2025 as the Biden-era average and only ten cases so far in 2026; Roberti committed the numbers would "rebound" while noting 2025's total fine amount was the highest in agency history0:54:410:56:17.

Pallone challenged PHMSA's January notice of limited enforcement discretion, calling it a blanket safety waiver tied to the president's "energy emergency"; Roberti said discretion would only be granted with a "demonstration that safety will not be undermined" and could be revoked0:56:370:57:58.

Matsui pressed Roberti on PHMSA overruling California and authorizing the Sable Offshore pipeline restart just six days after asserting jurisdiction, without environmental review or public comment as required by law; Roberti said an environmental review was "underway" and cited a 12-page inspection report1:49:411:50:111:51:52.

Crank confronted Roberti with a September 2025 rule limiting special-permit conditions that Roberti said he was "not aware of," then noted the draft bill would codify that rule, and questioned Deputy Administrator Ben Coachman citing his own prior INGA-authored comments in a rulemaking as a possible conflict of interest1:36:311:37:161:40:23.

Roberti disclosed a $9 million penalty — the highest proposed civil penalty in PHMSA history — for a Gulf of Mexico oil spill, issued at his direction0:55:31.

Roberti said the Satartia, Mississippi CO2 pipeline rupture resulted in a $2.8 million fine for failure to follow existing Part 195 requirements on storms, erosion, and geohazards1:20:36.

Meng highlighted PHMSA's termination of nine R&D grants ($7 million) on CO2/hydrogen pipeline safety at universities including Texas A&M and North Dakota State, after a spokesperson cited avoiding the "Green New Scam agenda"2:02:182:02:44.

Schrier detailed a BP Olympic Pipeline leak discovered by a blueberry farmer rather than company sensors, the 26th reportable incident on that line in 13 years, and noted the same pipeline caused a fatal 1999 explosion2:09:382:10:052:12:05.

Mullin said the bill provides at least $150 million less than the bipartisan T&I bill for replacing aging gas distribution pipelines, referencing the 2010 San Bruno explosion that killed eight people in his district2:34:272:34:51.

Metadata

CommitteeHouse Energy and Commerce Subcommittee on Energy
Chamber / CongressHouse · 119th Congress
Date2026-03-04
TypeHearing
Witnesses
The Honorable Paul Roberti — Administrator, Pipeline and Hazardous Materials Safety Administration
Videoyoutube
Transcript364 caption blocks · 24,105 words · 2:50:10 runtime
EventCongress.gov 119016